Jersey City / Newark Ave between Summit & JFK / MH 1-7 to 2-1
KEMSCO completed 65’ of excavation towards MH 2-1. (Trench activity completed)
Remaining footage to install 126’ of 6”, 10”, 4”PVC.
UTEC is set up to complete steel conduit installation by EOB Wednesday.
Welded pups on 6” & 10” Steel conduit.
Jersey City / Splice crew #2 MH 1-6 / Van Winkle**
UTEC splice crew 24/7 splice activity.
Jersey City / West Side Ave / MH 1-2
KEMSCO excavating for power supply for SJ Control Panel.
Excavate for Richmond for core drilling for oil control piping to control panel.
UTEC installing SJ Piping.
Weld crew @ WEY fabrication recirculation piping for MH 1-2.