PSE&G Electric Transmission Construction Update – August 5, 2015

Jersey City / Newark Ave between Summit & JFK / MH 1-7 to 2-1

KEMSCO supporting trench access for UTEC.

KEMSCO working roof modification on MH 2-1. Completed roof opening, need to make modification.

Road Plates, cones, drums, signs protect work zone.

UTEC installing last section of 10” steel conduit connecting MH 1-7 to 2-1. Completed.

UTEC welded 100” of 6” steel conduit, need 28’ to complete tie in from MH 1-7 to 2-1. (Complete tomorrow)

UTEC needs to install 185’ of 4” PVC (Complete Wednesday).

Jersey City / Splice crew #2 MH 1-6 / Van Winkle

UTEC splice crew 24/7 splice activity.

Jersey City / West Side Ave / MH 1-2

KEMSCO excavating for power supply for SJ Control Panel. (Completed)

KEMSCO framed out for control cabinets.

Excavate for Richmond for core drilling for oil control piping to control panel. (Completed)

UTEC installing SJ Piping.

Weld crew @ WEY fabrication recirculation piping for MH 1-2.

All-State supporting dewatering.

If colleagues or neighbors have any questions, please ask to send an email or call:

• william.cesario@pseg.com
• 1 – 877 – 678 – 5784

Residents who do not have access to electronic communications devices can call (201) 330 – 6629 for the electric transmission construction update.