Jersey City / James Ave & ST Paul’s Intersection
KEMSCO back filled & paved additional 35’ on roadway.
Half of ST Pauls intersection is paved to grade.
UTEC bent & welded 25’ section of 10” steel conduit.
Cut back, welded pup, bent & welded a 50’ X 6” steel conduit.
Road plates, cones, drums, signs protect work zone.
Jersey City / JFK – Newark Ave / Conduit Reconfiguration / H-2313
KEMSCO remove plates for UTEC to work in the intersection Newark Ave
And JFK BLVD and East on Newark Ave.
Back fill in the intersection of Newark Ave
And JFK BLVD back fill & paved to grade 75ft of roadway.
UTEC @ Newark Ave & JFK BLVD
Steel pipe @ 50ft each Pipe totals 100ft. Tues plan to finish tying
In from manhole 1-7 back to 1-6. UTEC will had a crew out to swab and mandrel
Manpower 2- foreman 6 Electricians 2- crane Operator
Note UTEC crew is 420ft away form cut & cap
Roof modification for M-H 2-1 will start on Thursday
Tues continue.
Jersey City / Newark Ave / SC H-4
RCC / BRASUSA poured concrete sidewalks, cubs, driveway.
Return date TBD to etch block pattern in uncured area.
RCC will need demob from lot under 78.
If colleagues or neighbors have any questions, please ask to send an email or call:
Residents who do not have access to electronic communications devices can call (201) 330 – 6629 for the electric transmission construction update.